공사지역/공사종류별 수주액,기성액,원도급 및 하도급공사 기성액
Back to top공사지역별 전체 · 공사종류별 총계
- Value of orders received
- Building construction Value of orders received
- Detached & tenement house Value of orders received
- Low-rise apartment(less than 5th floor) Value of orders received
- High-rise apartment(6~15 floor) Value of orders received
- APT(16 floor or more) Value of orders received
- Residential shop Value of orders received
- Market department store Value of orders received
- Office building Value of orders received
- Officetel Value of orders received
- Intelligent building Value of orders received
- Public building(less than 11th floor) Value of orders received
- Public building(11th floor more) Value of orders received
- Hotel & lodgings Value of orders received
- Educational facilities Value of orders received
- Hospital Value of orders received
- Church & temple Value of orders received
- Traditional style building Value of orders received
- Other cultural building Value of orders received
- Public & Performance Value of orders received
- Stadium & playground Value of orders received
- Exhibition pavilion Value of orders received
- Factory & workshop Value of orders received
- Machine installation (except plant) Value of orders received
- Value of construction completed
- Building construction Value of construction completed
- Detached & tenement house Value of construction completed
- Low-rise apartment(less than 5th floor) Value of construction completed
- High-rise apartment(6~15 floor) Value of construction completed
- APT(16 floor or more) Value of construction completed
- Residential shop Value of construction completed
- Market department store Value of construction completed
- Office building Value of construction completed
- Officetel Value of construction completed
- Intelligent building Value of construction completed
- Public building(less than 11th floor) Value of construction completed
- Public building(11th floor more) Value of construction completed
- Hotel & lodgings Value of construction completed
- Educational facilities Value of construction completed
- Hospital Value of construction completed
- Church & temple Value of construction completed
- Traditional style building Value of construction completed
- Other cultural building Value of construction completed
- Public & Performance Value of construction completed
- Stadium & playground Value of construction completed
- Exhibition pavilion Value of construction completed
- Factory & workshop Value of construction completed
- Machine installation (except plant) Value of construction completed
- Value of construction completed in original contract
- Building construction Value of construction completed in original contract
- Detached & tenement house Value of construction completed in original contract
- Low-rise apartment(less than 5th floor) Value of construction completed in original contract
- High-rise apartment(6~15 floor) Value of construction completed in original contract
- APT(16 floor or more) Value of construction completed in original contract
- Residential shop Value of construction completed in original contract
- Market department store Value of construction completed in original contract
- Office building Value of construction completed in original contract
- Officetel Value of construction completed in original contract
- Intelligent building Value of construction completed in original contract
- Public building(less than 11th floor) Value of construction completed in original contract
- Public building(11th floor more) Value of construction completed in original contract
- Hotel & lodgings Value of construction completed in original contract
- Educational facilities Value of construction completed in original contract
- Hospital Value of construction completed in original contract
- Church & temple Value of construction completed in original contract
- Traditional style building Value of construction completed in original contract
- Other cultural building Value of construction completed in original contract
- Public & Performance Value of construction completed in original contract
- Stadium & playground Value of construction completed in original contract
- Exhibition pavilion Value of construction completed in original contract
- Factory & workshop Value of construction completed in original contract
- Machine installation (except plant) Value of construction completed in original contract
- Value of construction completed in subcontract
- Building construction Value of construction completed in subcontract
- Detached & tenement house Value of construction completed in subcontract
- Low-rise apartment(less than 5th floor) Value of construction completed in subcontract
- High-rise apartment(6~15 floor) Value of construction completed in subcontract
- APT(16 floor or more) Value of construction completed in subcontract
- Residential shop Value of construction completed in subcontract
- Market department store Value of construction completed in subcontract
- Office building Value of construction completed in subcontract
- Officetel Value of construction completed in subcontract
- Intelligent building Value of construction completed in subcontract
- Public building(less than 11th floor) Value of construction completed in subcontract
- Public building(11th floor more) Value of construction completed in subcontract
- Hotel & lodgings Value of construction completed in subcontract
- Educational facilities Value of construction completed in subcontract
- Hospital Value of construction completed in subcontract
- Church & temple Value of construction completed in subcontract
- Traditional style building Value of construction completed in subcontract
- Other cultural building Value of construction completed in subcontract
- Public & Performance Value of construction completed in subcontract
- Stadium & playground Value of construction completed in subcontract
- Exhibition pavilion Value of construction completed in subcontract
- Factory & workshop Value of construction completed in subcontract
- Machine installation (except plant) Value of construction completed in subcontract
- Value of carry-over work
- Building construction Value of carry-over work
- Detached & tenement house Value of carry-over work
- Low-rise apartment(less than 5th floor) Value of carry-over work
- High-rise apartment(6~15 floor) Value of carry-over work
- APT(16 floor or more) Value of carry-over work
- Residential shop Value of carry-over work
- Market department store Value of carry-over work
- Office building Value of carry-over work
- Officetel Value of carry-over work
- Intelligent building Value of carry-over work
- Public building(less than 11th floor) Value of carry-over work
- Public building(11th floor more) Value of carry-over work
- Hotel & lodgings Value of carry-over work
- Educational facilities Value of carry-over work
- Hospital Value of carry-over work
- Church & temple Value of carry-over work
- Traditional style building Value of carry-over work
- Other cultural building Value of carry-over work
- Public & Performance Value of carry-over work
- Stadium & playground Value of carry-over work
- Exhibition pavilion Value of carry-over work
- Factory & workshop Value of carry-over work
- Machine installation (except plant) Value of carry-over work
Value of orders received
1994 87,295,851Million Won→2007 274,458,722Million Won▲ +214.4%
Building construction Value of orders received
1994 58,932,845Million Won→2007 163,742,321Million Won▲ +177.8%
Detached & tenement house Value of orders received
1994 1,865,405Million Won→2007 2,454,739Million Won▲ +31.6%
Low-rise apartment(less than 5th floor) Value of orders received
1994 980,175Million Won→2007 942,015Million Won▼ −3.9%
High-rise apartment(6~15 floor) Value of orders received
1994 13,669,207Million Won→2007 21,019,818Million Won▲ +53.8%
APT(16 floor or more) Value of orders received
1994 7,235,961Million Won→2007 50,299,832Million Won▲ +595.1%
Residential shop Value of orders received
1994 1,929,862Million Won→2007 9,115,890Million Won▲ +372.4%
Market department store Value of orders received
1994 4,288,265Million Won→2007 8,022,492Million Won▲ +87.1%
Office building Value of orders received
1994 5,804,660Million Won→2007 8,664,251Million Won▲ +49.3%
Officetel Value of orders received
1997 1,786,594Million Won→2007 2,131,089Million Won▲ +19.3%
Intelligent building Value of orders received
1997 494,138Million Won→2007 491,616Million Won▼ −0.5%
Public building(less than 11th floor) Value of orders received
1994 1,863,863Million Won→2007 3,826,813Million Won▲ +105.3%
Public building(11th floor more) Value of orders received
1997 215,107Million Won→2007 419,772Million Won▲ +95.1%
Hotel & lodgings Value of orders received
1994 1,282,803Million Won→2007 5,171,947Million Won▲ +303.2%
Educational facilities Value of orders received
1994 2,474,618Million Won→2007 8,440,263Million Won▲ +241.1%
Hospital Value of orders received
1994 1,043,921Million Won→2007 2,600,164Million Won▲ +149.1%
Church & temple Value of orders received
1994 716,846Million Won→2007 1,417,595Million Won▲ +97.8%
Traditional style building Value of orders received
1994 114,593Million Won→2007 47,571Million Won▼ −58.5%
Other cultural building Value of orders received
1997 114,101Million Won→2007 74,683Million Won▼ −34.5%
Public & Performance Value of orders received
1994 1,097,841Million Won→2007 845,693Million Won▼ −23.0%
Stadium & playground Value of orders received
1994 515,506Million Won→2007 1,017,500Million Won▲ +97.4%
Exhibition pavilion Value of orders received
1997 729,420Million Won→2007 1,527,201Million Won▲ +109.4%
Factory & workshop Value of orders received
1994 9,470,264Million Won→2007 17,706,033Million Won▲ +87.0%
Machine installation (except plant) Value of orders received
1994 1,546,749Million Won→2007 2,364,347Million Won▲ +52.9%
Value of construction completed
1994 68,057,102Million Won→2007 181,667,024Million Won▲ +166.9%
Building construction Value of construction completed
1994 46,645,697Million Won→2007 103,329,833Million Won▲ +121.5%
Detached & tenement house Value of construction completed
1994 1,809,737Million Won→2007 1,174,933Million Won▼ −35.1%
Low-rise apartment(less than 5th floor) Value of construction completed
1994 1,054,570Million Won→2007 510,200Million Won▼ −51.6%
High-rise apartment(6~15 floor) Value of construction completed
1994 12,503,488Million Won→2007 12,771,121Million Won▲ +2.1%
APT(16 floor or more) Value of construction completed
1994 4,992,033Million Won→2007 26,803,477Million Won▲ +436.9%
Residential shop Value of construction completed
1994 916,338Million Won→2007 5,699,068Million Won▲ +521.9%
Market department store Value of construction completed
1994 2,792,625Million Won→2007 5,421,429Million Won▲ +94.1%
Office building Value of construction completed
1994 4,770,647Million Won→2007 5,539,060Million Won▲ +16.1%
Officetel Value of construction completed
1997 705,159Million Won→2007 1,443,202Million Won▲ +104.7%
Intelligent building Value of construction completed
1997 626,947Million Won→2007 852,329Million Won▲ +35.9%
Public building(less than 11th floor) Value of construction completed
1994 1,909,856Million Won→2007 3,321,612Million Won▲ +73.9%
Public building(11th floor more) Value of construction completed
1997 358,149Million Won→2007 458,626Million Won▲ +28.1%
Hotel & lodgings Value of construction completed
1994 904,077Million Won→2007 2,104,836Million Won▲ +132.8%
Educational facilities Value of construction completed
1994 1,872,233Million Won→2007 5,617,439Million Won▲ +200.0%
Hospital Value of construction completed
1994 938,579Million Won→2007 2,072,260Million Won▲ +120.8%
Church & temple Value of construction completed
1994 338,327Million Won→2007 950,853Million Won▲ +181.0%
Traditional style building Value of construction completed
1994 118,863Million Won→2007 34,370Million Won▼ −71.1%
Other cultural building Value of construction completed
1997 111,594Million Won→2007 84,198Million Won▼ −24.5%
Public & Performance Value of construction completed
1994 808,848Million Won→2007 706,143Million Won▼ −12.7%
Stadium & playground Value of construction completed
1994 374,063Million Won→2007 798,959Million Won▲ +113.6%
Exhibition pavilion Value of construction completed
1997 447,478Million Won→2007 1,176,413Million Won▲ +162.9%
Factory & workshop Value of construction completed
1994 7,389,254Million Won→2007 12,985,780Million Won▲ +75.7%
Machine installation (except plant) Value of construction completed
1994 912,401Million Won→2007 1,132,783Million Won▲ +24.2%
Value of construction completed in original contract
1994 52,960,030Million Won→2007 121,741,956Million Won▲ +129.9%
Building construction Value of construction completed in original contract
1994 37,233,500Million Won→2007 67,556,640Million Won▲ +81.4%
Detached & tenement house Value of construction completed in original contract
1994 1,661,773Million Won→2007 865,689Million Won▼ −47.9%
Low-rise apartment(less than 5th floor) Value of construction completed in original contract
1994 760,728Million Won→2007 324,076Million Won▼ −57.4%
High-rise apartment(6~15 floor) Value of construction completed in original contract
1994 10,464,936Million Won→2007 7,954,297Million Won▼ −24.0%
APT(16 floor or more) Value of construction completed in original contract
1994 4,641,979Million Won→2007 17,244,567Million Won▲ +271.5%
Residential shop Value of construction completed in original contract
1994 766,254Million Won→2007 3,971,597Million Won▲ +418.3%
Market department store Value of construction completed in original contract
1994 2,193,289Million Won→2007 3,925,387Million Won▲ +79.0%
Office building Value of construction completed in original contract
1994 3,412,861Million Won→2007 3,954,529Million Won▲ +15.9%
Officetel Value of construction completed in original contract
1997 469,814Million Won→2007 924,501Million Won▲ +96.8%
Intelligent building Value of construction completed in original contract
1997 532,582Million Won→2007 572,449Million Won▲ +7.5%
Public building(less than 11th floor) Value of construction completed in original contract
1994 1,422,837Million Won→2007 2,139,473Million Won▲ +50.4%
Public building(11th floor more) Value of construction completed in original contract
1997 205,725Million Won→2007 291,062Million Won▲ +41.5%
Hotel & lodgings Value of construction completed in original contract
1994 727,082Million Won→2007 1,420,656Million Won▲ +95.4%
Educational facilities Value of construction completed in original contract
1994 1,440,902Million Won→2007 3,452,383Million Won▲ +139.6%
Hospital Value of construction completed in original contract
1994 687,688Million Won→2007 1,275,664Million Won▲ +85.5%
Church & temple Value of construction completed in original contract
1994 255,821Million Won→2007 579,109Million Won▲ +126.4%
Traditional style building Value of construction completed in original contract
1994 91,418Million Won→2007 24,779Million Won▼ −72.9%
Other cultural building Value of construction completed in original contract
1997 87,851Million Won→2007 51,726Million Won▼ −41.1%
Public & Performance Value of construction completed in original contract
1994 582,606Million Won→2007 439,413Million Won▼ −24.6%
Stadium & playground Value of construction completed in original contract
1994 244,071Million Won→2007 467,431Million Won▲ +91.5%
Exhibition pavilion Value of construction completed in original contract
1997 333,631Million Won→2007 827,302Million Won▲ +148.0%
Factory & workshop Value of construction completed in original contract
1994 5,515,025Million Won→2007 8,985,914Million Won▲ +62.9%
Machine installation (except plant) Value of construction completed in original contract
1994 659,240Million Won→2007 852,787Million Won▲ +29.4%
Value of construction completed in subcontract
1994 15,097,072Million Won→2007 59,925,068Million Won▲ +296.9%
Building construction Value of construction completed in subcontract
1994 9,412,197Million Won→2007 35,773,192Million Won▲ +280.1%
Detached & tenement house Value of construction completed in subcontract
1994 147,964Million Won→2007 309,243Million Won▲ +109.0%
Low-rise apartment(less than 5th floor) Value of construction completed in subcontract
1994 293,842Million Won→2007 186,123Million Won▼ −36.7%
High-rise apartment(6~15 floor) Value of construction completed in subcontract
1994 2,038,551Million Won→2007 4,816,823Million Won▲ +136.3%
APT(16 floor or more) Value of construction completed in subcontract
1994 350,053Million Won→2007 9,558,910Million Won▲ +2630.7%
Residential shop Value of construction completed in subcontract
1994 150,083Million Won→2007 1,727,471Million Won▲ +1051.0%
Market department store Value of construction completed in subcontract
1994 599,335Million Won→2007 1,496,041Million Won▲ +149.6%
Office building Value of construction completed in subcontract
1994 1,357,786Million Won→2007 1,584,530Million Won▲ +16.7%
Officetel Value of construction completed in subcontract
1997 235,344Million Won→2007 518,700Million Won▲ +120.4%
Intelligent building Value of construction completed in subcontract
1997 94,365Million Won→2007 279,880Million Won▲ +196.6%
Public building(less than 11th floor) Value of construction completed in subcontract
1994 487,018Million Won→2007 1,182,139Million Won▲ +142.7%
Public building(11th floor more) Value of construction completed in subcontract
1997 152,424Million Won→2007 167,564Million Won▲ +9.9%
Hotel & lodgings Value of construction completed in subcontract
1994 176,995Million Won→2007 684,179Million Won▲ +286.6%
Educational facilities Value of construction completed in subcontract
1994 431,331Million Won→2007 2,165,055Million Won▲ +401.9%
Hospital Value of construction completed in subcontract
1994 250,890Million Won→2007 796,595Million Won▲ +217.5%
Church & temple Value of construction completed in subcontract
1994 82,506Million Won→2007 371,743Million Won▲ +350.6%
Traditional style building Value of construction completed in subcontract
1994 27,444Million Won→2007 9,591Million Won▼ −65.1%
Other cultural building Value of construction completed in subcontract
1997 23,742Million Won→2007 32,472Million Won▲ +36.8%
Public & Performance Value of construction completed in subcontract
1994 226,242Million Won→2007 266,729Million Won▲ +17.9%
Stadium & playground Value of construction completed in subcontract
1994 129,992Million Won→2007 331,528Million Won▲ +155.0%
Exhibition pavilion Value of construction completed in subcontract
1997 113,846Million Won→2007 349,110Million Won▲ +206.7%
Factory & workshop Value of construction completed in subcontract
1994 1,874,228Million Won→2007 3,999,865Million Won▲ +113.4%
Machine installation (except plant) Value of construction completed in subcontract
1994 253,160Million Won→2007 279,995Million Won▲ +10.6%
Value of carry-over work
1994 89,227,352Million Won→2007 340,345,467Million Won▲ +281.4%
Building construction Value of carry-over work
1994 61,831,304Million Won→2007 203,525,660Million Won▲ +229.2%
Detached & tenement house Value of carry-over work
1994 1,113,821Million Won→2007 2,394,490Million Won▲ +115.0%
Low-rise apartment(less than 5th floor) Value of carry-over work
1994 842,986Million Won→2007 988,259Million Won▲ +17.2%
High-rise apartment(6~15 floor) Value of carry-over work
1994 16,079,338Million Won→2007 31,960,315Million Won▲ +98.8%
APT(16 floor or more) Value of carry-over work
1994 12,802,626Million Won→2007 83,917,161Million Won▲ +555.5%
Residential shop Value of carry-over work
1994 2,826,709Million Won→2007 14,126,313Million Won▲ +399.7%
Market department store Value of carry-over work
1994 3,866,108Million Won→2007 8,508,709Million Won▲ +120.1%
Office building Value of carry-over work
1994 6,644,647Million Won→2007 7,894,185Million Won▲ +18.8%
Officetel Value of carry-over work
1997 2,239,966Million Won→2007 2,717,141Million Won▲ +21.3%
Intelligent building Value of carry-over work
1997 1,141,390Million Won→2007 1,083,836Million Won▼ −5.0%
Public building(less than 11th floor) Value of carry-over work
1994 1,698,035Million Won→2007 2,907,925Million Won▲ +71.3%
Public building(11th floor more) Value of carry-over work
1997 229,201Million Won→2007 376,683Million Won▲ +64.3%
Hotel & lodgings Value of carry-over work
1994 1,250,251Million Won→2007 5,553,213Million Won▲ +344.2%
Educational facilities Value of carry-over work
1994 1,700,122Million Won→2007 6,707,273Million Won▲ +294.5%
Hospital Value of carry-over work
1994 1,223,800Million Won→2007 3,067,299Million Won▲ +150.6%
Church & temple Value of carry-over work
1994 616,199Million Won→2007 1,490,452Million Won▲ +141.9%
Traditional style building Value of carry-over work
1994 59,323Million Won→2007 84,099Million Won▲ +41.8%
Other cultural building Value of carry-over work
1997 59,123Million Won→2007 47,388Million Won▼ −19.8%
Public & Performance Value of carry-over work
1994 979,469Million Won→2007 801,372Million Won▼ −18.2%
Stadium & playground Value of carry-over work
1994 431,119Million Won→2007 913,513Million Won▲ +111.9%
Exhibition pavilion Value of carry-over work
1997 508,136Million Won→2007 1,067,930Million Won▲ +110.2%
Factory & workshop Value of carry-over work
1994 5,864,664Million Won→2007 11,832,992Million Won▲ +101.8%
Machine installation (except plant) Value of carry-over work
1994 1,156,292Million Won→2007 2,200,029Million Won▲ +90.3%
Data source
- Organization
- 통계청
- Dataset
- 산업세분류 및 조직형태별 총괄
- Provider
- KOSIS 국가통계포털
- Period
- 1994 ~ 2007
- As of
- 2026-08-29
- Processing
- KOSIS OpenAPI 로 연간 전국값을 받아 그대로 사용. 가공 없음.
Other surveys in this category
- Construction Industry Survey1 tables · 102 items
- Construction Business Trend Survey13 tables · 159 items
- Building Permit, Start and Completion Statistics4 tables · 26 items
- Building Statistics1 tables · 113 items
- Urban Redevelopment Project Status5 tables · 26 items
- Overseas Construction Orders Statistics3 tables · 78 items